The Port of Huntsville is well into an extensive list of capital improvement projects forecasted in the previous fiscal year. Projects tell a story, and the narrative is that the Port of Huntsville is experiencing rapid growth in industry and passenger volume. The budget for projects under contract or under construction totals $62,071,261. Here is a list of the projects slated for FY24:
- New Employee Parking Lot
- Expected Completion: December 2023
- Contractor: Wiregrass Construction
- Engineer: Sain Associates
- Budget: $3.2 million
- Cell Phone Waiting Lot
- Expected Completion: December 2023
- Contractor: Wiregrass Construction
- Engineer: Sain Associates
- Budget: $730,000
- Air Cargo Warehouse
- Expected Completion Date: Winter 2023
- Contractor: Fite Building Company
- Architect: Barge Design Solutions
- Budget: $17 million
- Concourse connector project
- Ramp Usage Start: November 2023
- Ramp Usage End: December 2024
- Contractor: Robins & Morton
- Architect: EDT-THA Architecture
- Budget: $13.99 million
- Taxiway W Rehabilitation
- Start Date: February 5, 2024
- Phase 1 Completion: July 2024
- Contractor: Wiregrass Construction
- Engineer: Morell Engineering
- Budget $9.2 million
- Signature Aviation Terminal Expansion
- Expected Completion: August 2024
- Contractor: Robins & Morton
- Budget: $12.1 million
- F2 Connector Relocation
- Start Date: September 2024
- Completion Date: November 2024
- Contractor: SJ&L General Contractors
- Engineer: Barge Design Solutions
- Budget: $2.8 million
- Rental Car Surface Return Lot
- Start Date: December 2023
- Contractor: Robins & Morton
- Architect: KPS Group
- Budget: $3 million
- Perimeter Fence Replacement
- Start Date: TBD
- Contractor: TUSCO
- Architect: Goodwyn, Mills, Cawood
- Budget: $800,000
Additional capital improvements totaling more than $80.1 million are anticipated to begin construction or design in FY24.